Timeline

Activity Proposed Date
Start fabrication 1/4/2011
Start module construct 1/10/2011
Keel laying ceremony 4/11/2011
Erection complete 7/05/2012
Move out of vessel 9/21/2012
Launch ceremony 10/13/2012
Start builder's dock trials 3/25/2013
Dry dock period 4/12/2013
Builder's sea trials 4/15/2013
Acceptance trials 5/13/2013
Delivery 7/26/2013

The Sikuliaq is expected to arrive in Seward in late 2013. Science operations will begin in early 2014.